Anticipated Timeline

  • June 1, 2023 - Bids Available
  • June 8, 2023 - Pre-bid Meeting at City Hall
  • June 29, 2023 - Bid Opening
  • July 10, 2023 - City Council to Approve Contract
  • July 12, 2023 - Downtown Development Authority Awards Contract
  • August 14, 2023 - Anticipated Construction Start Date
  • April 2024 - Anticipated Project Completion

Scope of Work

  • Replacement of ballfield lighting
  • Renovation of warming house building at ballfield
  • Expansion of existing deck at Riverfront Park
  • Construction of public restroom at Riverfront Park
  • Install EV Charging station in City parking lot by the library
Riverfront Park Plan Comp
Full Project Plan Rendering