Streetscape and Ballfield Improvements

Anticipated Timeline

  • June 1, 2023 - Bids Available
  • June 8, 2023 - Pre-bid Meeting at City Hall
  • June 29, 2023 - Bid Opening
  • July 10, 2023 - City Council to Approve Contract
  • July 12, 2023 - Downtown Development Authority Awards Contract
  • August 2023 - Anticipated Construction Start Date
  • October 2024 - Anticipated Project Completion

Scope of Work

  • Streetscape improvements along:
    • North & South Bridge Street (M-100) from Scott to Main Street
    • Resurfacing of roadway between Front and Main Street
  • West River between Harrison and South Bridge Street: streetscape improvements
  • Site improvements at Fitzgerald Memorial ballfield
  • Riverbank Improvements along Grand River
Fitzgerald Field Plan Rendering Comp